DANCE B project: Our Timeline in Brief
DANCE BLIND PROJECT
Project Start-up Phase – Month 1
15 September – 14 October
1. Overall Objective
The first month focuses on establishing the project’s collaborative structure, defining roles and responsibilities, and setting up effective coordination and communication procedures.
The main objective is to ensure the coordinated development of the project’s artistic, scientific, technological and social dimensions, with meaningful participation of people with visual impairments and accessibility considerations integrated throughout the process.
2. Project Partners and Key Responsibilities
ESAI EN ROI – Artistic and Overall Coordination: Overall project management, artistic direction, partner coordination, timeline monitoring, communication and evaluation.
Sense LAB – Scientific and Technological Support: Development of technological tools, exploration of tactile movement representation and movement-to-sound interaction, and identification of technical requirements.
2nd Municipal Community of the Municipality of Thessaloniki: Local networking, organisational support, identification of potential venues and connections with community organisations.
Deputy Mayor for Social Policy of the Municipality of Chania and Municipal KDAPmeA (Creative Activity Centres for People with Disabilities): Engagement with social services, identification of accessibility and participation requirements, and communication with potential participants and support professionals.
Detailed responsibilities and communication procedures will be agreed upon during the initial coordination meeting.
3. Key Activities
During the first month, the project will focus on:
Establishing the project team and holding initial coordination meetings.
Defining roles, responsibilities and communication channels.
Contacting partner organisations and identifying accessibility requirements.
Agreeing on shared principles of inclusion, co-creation and meaningful participation of people with visual impairments.
Establishing decision-making and conflict-resolution procedures.
Scheduling regular scientific, artistic and organisational meetings.
Preparing an initial work plan, including responsibilities, deadlines and expected outcomes.
4. Coordination and Decision-Making Framework
A collaborative decision-making process will be established, based on clearly defined responsibilities and documented agreements.
The process will include:
Identification and documentation of issues or proposals.
Recommendations from the partner responsible for the relevant area.
Consultation among the relevant partners and stakeholders.
Decisions based primarily on consensus, with clearly defined responsibilities when consensus cannot be reached.
Documentation of decisions, assigned responsibilities and implementation deadlines.
Decisions affecting the overall project scope, budget or timeline will require approval from the relevant partners.
5. Regular Meetings and Monitoring
Scientific and Artistic Team
Frequency: Every two weeks.
Proposed day: Thursday.
Proposed time: 12:30–13:30, subject to confirmation.
Focus: Monitoring artistic, scientific and technological progress, addressing accessibility issues, reviewing testing requirements and agreeing on next steps.
Organisational Team
Frequency: Once per month.
Focus:
Review of project progress and deliverables.
Financial monitoring and budget review.
Assessment of organisational effectiveness.
Evaluation of partner communication and collaboration.
Identification of risks and corrective actions.
Definition of priorities for the following month.
All meetings will be documented through concise minutes recording decisions, pending issues, responsibilities and deadlines.
6. Monthly Organisational Evaluation
At the end of the month, a short internal evaluation will assess:
Strengths: What worked effectively and should be maintained.
Challenges: Delays, unclear responsibilities, communication difficulties or accessibility barriers.
Improvements: Practical adjustments to workflows, collaboration and task allocation.
Follow-up: Assignment of responsibilities and deadlines for implementing improvements.
An action-tracking table will be maintained to ensure that evaluation leads to concrete improvements.
7. Expected Deliverables
By the end of the first month, the project is expected to produce:
Minutes of the kick-off and initial coordination meetings.
A list of project partners and key contact persons.
An initial allocation of roles and responsibilities.
A preliminary work plan with assigned tasks and deadlines.
An agreed decision-making framework.
A schedule of regular scientific, artistic and organisational meetings.
An initial assessment of accessibility requirements and issues requiring further investigation.
8. Month 1 Completion Criteria
The start-up phase will be considered successfully completed when:
All key partners and communication contacts have been confirmed.
Roles and responsibilities have been agreed upon.
Decision-making and documentation procedures have been established.
Regular meeting schedules have been confirmed.
An initial work plan and deliverables tracker have been created.
Initial accessibility needs have been identified and actions for addressing them have been outlined.
Overall milestone: By 14 October, DANCE BLIND will have an established partnership and coordination structure, agreed working procedures, a preliminary implementation plan and a shared framework for inclusive and accessible project development.